Principal designers and CDM consultants: costs, duties and F10 notification

Principal designer services for a small project usually start at about £1,000–£2,000. See when CDM 2015 requires a principal designer, when to send an F10 to HSE, what the three CDM documents are and how to check a CDM consultant's competence.

Principal designer needed
when more than one contractor
Small project fee
from about £1,000–£2,000
F10 notification
over 30 working days with more than 20 workers at once, or over 500 person days
CDM coordinator
replaced by principal designer in 2015
Building Regulations PD
separate role in England; can be the same firm
Extension under constructionDesign drawingsHealth and safety file 6 ft
A principal designer reviewing drawings beside a house extension under construction, with a six foot figure for scale. Illustrative.

Principal designers and CDM consultants

Search your site postcode to see who covers it, check their paperwork and contact them directly.

See all principal designers and CDM consultants
We're adding principal designers and CDM consultants now. Tell us what you need and we'll point you to a local option, or list your business.

A CDM consultant helps clients and project teams meet the Construction (Design and Management) Regulations 2015 (CDM 2015). The most common appointment is the principal designer, which the law requires whenever more than one contractor will work on a project. Published fee guides say principal designer services for a small project usually start at about £1,000–£2,000, and on projects worth £5 million or more one published fee schedule estimates about 0.16%–0.22% of the build cost.

Principal designer, CDM adviser or CDM coordinator?

More than one contractor

Principal designer

Appointed in writing by the client to plan, manage, monitor and co-ordinate health and safety in the pre-construction phase, and to prepare the health and safety file.

Must be a designer with control over the pre-construction phase.

Clients who want support

CDM adviser (CDM advisor)

Advises the client on its duties, appointments, pre-construction information and HSE notification, without taking on a legal role itself.

The scope is agreed with the client, not set by the regulations.

Older projects and job titles

CDM coordinator

The role under the old CDM 2007 regulations. CDM 2015 came into force on 6 April 2015 and replaced it with the principal designer, after a transition that ended on 6 October 2015.

HSE says the principal designer is not a direct replacement: the duties are different.

Who needs a principal designer?

CDM 2015 applies to construction work in Great Britain, whatever its size. Where there is more than one contractor, or it is reasonably foreseeable there will be, the client must appoint in writing:

A principal designer Legal

A designer with control over the pre-construction phase. On smaller projects it can be an individual.

A principal contractor Legal

A contractor who plans, manages and co-ordinates the construction phase and draws up the construction phase plan.

When to appoint Timing

As soon as is practicable, and in any event before the construction phase begins. If the client doesn't appoint them, the client must carry out the principal designer's and principal contractor's duties itself.

Competence

Anyone appointed must have the skills, knowledge and experience, and, if an organisation, the organisational capability, to do the role. The person appointing them must take reasonable steps to check.

Client duties under CDM 2015

A commercial client is anyone having construction work done as part of a business. These duties apply on every project, including single-contractor jobs.

  • Make suitable arrangements. Allow enough time and resources for the work to be done safely, including welfare facilities.
  • Provide pre-construction information. As soon as practicable, to every designer and contractor being considered or appointed.
  • Make sure there is a construction phase plan before the construction phase begins.
  • Make sure a health and safety file is prepared by the principal designer where there is one, and keep it available.
  • Check the principal designer and principal contractor are doing their jobs, taking reasonable steps.
  • Pass the file on to the new owner if you sell the building.

Householders (domestic clients)

A householder having work done on their own home, or the home of a family member, not as part of a business, is a domestic client. Their client duties pass automatically: to the contractor on a single-contractor job, or to the principal contractor where there is more than one. A principal designer can take them on instead, but only with a written agreement.

If a householder doesn't appoint a principal designer and principal contractor where they are needed, the designer in control of the pre-construction phase becomes the principal designer and the contractor in control of the construction phase becomes the principal contractor. So most householders don't need to hire a CDM consultant, but on an extension with separate trades, it is worth agreeing in writing who holds each role.

F10 notification: when to tell HSE

Over 30 working daysof construction work, with more than 20 workers on site at the same time at any point
Over 500person days of construction work in total, the alternative trigger

A project is notifiable if it meets either test. HSE's guidance says every day construction work is likely to take place counts, including weekends and bank holidays.

  1. Who notifiesThe client. On domestic projects, the contractor or principal contractor notifies, or the principal designer if there is a written agreement.
  2. WhenAs soon as is practicable before the construction phase begins.
  3. HowOnline, using HSE's F10 form. HSE no longer accepts paper forms, email or post. You get a serial number to update the notification later.
  4. Display itA copy must be clearly displayed in the site office where workers can read it, and kept up to date.

The three CDM documents

DocumentWho prepares itWhen it is needed
Pre-construction informationThe client, helped by the principal designerEvery project. Given to designers and contractors bidding for or appointed to the work.
Construction phase planThe principal contractor, or the contractor on a single-contractor jobEvery project. Drawn up before the site is set up, setting out health and safety arrangements and site rules, and reviewed as work goes on.
Health and safety fileThe principal designer, or the principal contractor if the designer's appointment ends firstProjects with more than one contractor. Information for future work on the building, handed to the client at the end.

CDM principal designer or Building Regulations principal designer?

CDM principal designerBuilding Regulations principal designer
LawCDM 2015Building Regulations, as amended in 2023
WhereGreat BritainEngland
PurposeHealth and safety of workers and others affectedDesign work complies with building regulations
When neededMore than one contractorMore than one contractor

Each role has its own competence requirements. The same person or firm can hold both: instead of making a separate appointment, the client can certify in writing that the CDM principal designer is also the Building Regulations principal designer. On domestic projects, if the householder doesn't appoint one, the designer in control of the design phase becomes the Building Regulations principal designer by default.

What principal designer services cost

Most CDM consultants charge a fixed fee on small projects and a percentage of the build cost on larger ones. These ranges come from consultants' published fee guides, usually excluding VAT.

£1,000–£2,000principal designer or CDM support on a small project
£2,500–£5,000in one published fee schedule for contracts worth £200,000 to £1 million (a minimum fee at the lower end, estimates above)
0.16%–0.22%of build cost on projects worth £5 million or more, in one published fee schedule
  1. Appointment or adviceTaking on the principal designer role carries legal duties and usually costs more than advising the client.
  2. Project value and complexityBigger, notifiable projects mean more design reviews, meetings and paperwork.
  3. Site visits and meetingsAgree how many are included and what extras cost.
  4. One role or twoTaking on the Building Regulations principal designer role as well adds work.
Compare quotes properly

Check whether each quote is for the principal designer appointment or only advice, whether it covers the pre-construction information, the health and safety file and F10 notification, how many meetings and visits are included, and whether VAT and travel are extra.

What to check before you hire

Ask to see membership certificates and insurance, and check them on the body's own register.

APS (Association for Project Safety)

A professional institution for construction health and safety risk management, focused on CDM. Its website has a find-a-member search.

IOSH chartered membership (CMIOSH)

Chartered Member of IOSH, which requires senior experience, an assessment and ongoing CPD.

OSHCR

The Occupational Safety and Health Consultants Register lists consultants with chartered-level membership of a participating body, professional indemnity insurance and up-to-date CPD. HSE points people to it.

RIBA Principal Designer Register

For RIBA chartered architects who show they meet the competence criteria for the CDM and Building Regulations principal designer roles.

Professional indemnity insurance

Covers claims arising from poor advice or design co-ordination. OSHCR requires it of registered consultants.

Wider health and safety support

Many CDM consultants also offer site audits, RAMS and a retained competent person service. Our separate guide to health and safety consultants covers these services and their costs. Before refurbishment or demolition, you may also need an asbestos survey.

Questions to ask a CDM consultant

  • Are you quoting to be principal designer, or to advise?
  • Is that the CDM principal designer, the Building Regulations principal designer, or both?
  • Are you an APS member, CMIOSH or on OSHCR? Can I see your certificates?
  • What professional indemnity insurance do you carry?
  • Will you handle the F10 notification if the project is notifiable?
  • How many meetings and site visits are included, and does the price include VAT?

Prices in this guide are typical ranges from suppliers' published price lists and cost guides. They change and vary by area, so always confirm the price with the supplier before you book. Rules, fees and tax rates are checked against official sources.

Principal designers and CDM consultants questions

What does a CDM consultant do?

A CDM consultant helps clients and project teams meet the Construction (Design and Management) Regulations 2015. They either take on the principal designer role, if they are a designer with control over the pre-construction phase, or act as a CDM adviser, helping the client with appointments, pre-construction information, HSE notification and the health and safety file.

What is a principal designer?

Under CDM 2015, a principal designer is a designer appointed in writing by the client to plan, manage, monitor and co-ordinate health and safety in the pre-construction phase. They help the client gather pre-construction information, work with other designers to eliminate or control foreseeable risks, and prepare the health and safety file.

When do you need a principal designer?

Under CDM 2015, a client must appoint a principal designer and a principal contractor in writing whenever more than one contractor will work on a project, or it is reasonably foreseeable that more than one will. The appointments must be made as soon as practicable and before construction starts. If the client doesn't appoint them, the client must carry out those duties itself.

How much does a principal designer cost?

Consultants' published fee guides say principal designer services for a small project usually start at about £1,000 to £2,000, excluding VAT. On projects worth £5 million or more, one published fee schedule estimates about 0.16% to 0.22% of the build cost, with the percentage falling as project value rises.

When do you need to submit an F10 notification?

A construction project must be notified to HSE if the work will last longer than 30 working days with more than 20 workers on site at the same time at any point, or will exceed 500 person days. The client notifies HSE online using the F10 form as soon as practicable before the construction phase begins, and a copy must be displayed in the site office.

What happened to the CDM coordinator?

The CDM coordinator was a role under the CDM 2007 regulations. CDM 2015 came into force on 6 April 2015 and replaced it with the principal designer, with a transition period for existing projects that ended on 6 October 2015. HSE says the principal designer is not a direct replacement, because the duties are different.

What is a construction phase plan?

A construction phase plan sets out the health and safety arrangements and site rules for a construction project. Every project needs one under CDM 2015. It is drawn up by the principal contractor, or by the contractor on a single-contractor job, before the site is set up, and reviewed as the work goes on.

Is the Building Regulations principal designer the same as the CDM principal designer?

No. In England, the Building Regulations principal designer makes sure design work complies with building regulations, while the CDM principal designer manages health and safety risks. The same person or firm can do both: instead of a separate appointment, the client can certify in writing that the CDM principal designer is also the Building Regulations principal designer.

Do householders need a principal designer?

Householders are domestic clients under CDM 2015, and their duties normally pass to the contractor or principal contractor. If a householder doesn't appoint a principal designer on a job with more than one contractor, the designer in control of the pre-construction phase becomes the principal designer by default.